We have created this Traders page to help keep owners and traders of Chinatown informed and up to date on activities and construction works happening in the precinct. 

CONSTRUCTION INFO:

  • Asphalt is scheduled to be laid on Carnarvon Street in late January.

  • The new Roebuck Bay Lookout is open to the community from this weekend (Friday 16 November 2018). Read the full story here.

  • Construction in Chinatown: Monday 8 October - Saturday 22 December 2018

    Roads will re-open from 22 December 2018. From mid-February there will be short term road closures and traffic re-directions occurring while hard and soft landscaping is being completed (shade structures, planting etc.).  Estimated project finish is April/ May 2019.

  • Road-workers onsite: Monday to Saturday 7am – 5pm each week

  • Pedestrian access will be maintained throughout construction with all shops open as normal.

  • The Chinatown Revitalisation Project is assisting with deliveries and rubbish collection while roads are closed.

  • Chinatown traders and community queries: Talei Howell-Price, Chinatown Investment & Development Coordinator, 0428 916 149 or talei.howell-price@broome.wa.gov.au or pop into Chinatown HQ (see “Contact” page for HQ details).

  • Construction queries please contact Downer EDI Works Pty Ltd: chinatown.broome@downeredi.com.au

  • The Master Plan has been prepared to guide the Chinatown Revitalisation Project on public realm improvements that can be implemented to revitalise Chinatown and ensure the precinct remains the ‘heart and soul’ of Broome. To view or download a copy of The Master Plan, click here.

TRADER SUPPORT, HINTS & TIPS:

  • For Chinatown traders wishing to use the Broome Chinatown logo in their business collateral, please download the logo here along with the style guide here. Please note the logo already has the exclusion zone applied for your convenience.

  • Traders received a copy of the Small Business Development Commission booklet ‘Preparing for public works - a guide for small business’ to help assist with preparing for the road works. To download a copy, click here. You can also access the ‘Preparing for public works - interactive tools for small business’ booklet to further develop your ideas. To download a copy, click here.
    More information is available on the Small Business Development Corporation website or contact them direct: policy@smallbusiness.wa.gov.au

  • Free marketing materials are available to traders including ‘open’ signs and lanterns, and festoon lighting strands during cruise ship visits. Head to Chinatown HQ to collect some (see “Contact” page for HQ details).

  • Take advantage of special events happening in Chinatown including the Cruise Ships, Spot the Window Competition, Magnet Puzzle Challenge, Halloween and Christmas. Click the See & Do page for upcoming events and activities.

  • Traders of Chinatown are welcome to borrow the Chinatown HQ gazebos for any upcoming activities or events within the Chinatown precinct. For further information on how to book a gazebo, please contact the Chinatown Investment & Development Coordinator Talei on 0428 916 149 or email talei.howell-price@broome.wa.gov.au

CURRENT UPDATES:

  • From Wednesday 9 January to Friday 15 March Chinatown HQ will be open Wednesdays & Fridays only 8am - 4pm.

  • From Monday 17 December to Tuesday 8 January Chinatown HQ will be closed.

  • The November Newsletter for Chinatown Broome is now available online. Please click here to view.

  • The Chinatown Public Art and Interpretation Strategy is available to view online, to view or download a copy, click here.

  • New timed 2 hour free parking will be in place for some central locations within Chinatown during the wet season to allow for consistent turnover of customer parking. Free all-day parking is available at the Visitor Centre and Paspaley Plaza off Short Street and additional free all-day parking will be available on Male Oval off Carnarvon Street.

2018-10-05_Chinatown_504x504 FB_Post_HR copy.jpg

Chinatown road closures and detours

  • It’s business as usual when the major streetscape upgrades commence. Read all about it in our latest media release here.

  • Updated project factsheets are now available on our Project Information tab. These will also be available at the Chinatown Revitalisation Project team information marquee during Friday late night trading.

Check back here for more updates as they occur.

PAST UPDATES:

  • Look out for adverts in the local Broome Advertiser promoting shopping in Chinatown during construction. Including discount coupons and special Chinatown Construction Sales.

  • Small activities grants available to all Chinatown traders to encourage them to provide additional in store activities and participate in the precincts planned community events. Traders can contact the Chinatown Investment & Development Coordinator Talei on 0428 916 149 or email talei.howell-price@broome.wa.gov.au for further information. (NOW CLOSED).

  • The Chinatown Spot the Window Competition commences on Monday 26 November. To read all about it, click here.

  • The hunt is on for limited edition magnet puzzle pieces in Chinatown. Read all about it in our latest media release here.

  • Artists for Chinatown artworks have been announced, which include nationally recognised artists Nicole and Alex Mickel and Nic Compton. To read the full story, please click here.

  • The October Newsletter for Chinatown Broome is now available online. Please click here to view.

  • The September Newsletter for Chinatown Broome is now available online. Please click here to view.

  • Construction is commencing soon in Chinatown with road closures and detours occurring from Monday 8 October until April 2019. Pedestrian access will be maintained throughout construction with all shops open as normal. Come and be a part of it and support Chinatown shops through the transformation. Read the full article here.The August Newsletter for Chinatown Broome is now available online. Please click here to view.

  • Downer EDI Works have been awarded contract for streetscape and public realm improvement works, which include the Carnarvon St and Dampier Tce upgrades commencing this month (September 2018). To read the full story, please click here.

  • On 3 September 2018, Harby Studios ran a marketing workshop for Chinatown Traders. This workshop covered low cost marketing initiatives that could be implemented during and post construction.

ChinatownStreetscape_FinalRender.jpg

Artist's impression of Carnarvon Street

  • The RFQ for the Carnarvon Street and Dampier Terrace street works is currently being advertised and we expect to have a contractor on board by August 2018. A detailed program for the construction works will be developed with the preferred contractor and we will be keeping you informed as this progresses, however a key focus will be to stage and schedule the works to prevent disruption to business.

  • The July Newsletter for Chinatown Broome is now available online. Please click here to view.

  • Project planners and managers walked around town week commencing 25 June 2018 to chat to traders about upcoming works in their area.

  • The June Newsletter for Chinatown Broome is now available online. Please click here to view.